248 km
transmission line
500 kV
Largest
transmission project undertaken by BC Hydro in 30 years
Challenges
- Strengthen the transmission system from the Northern and Southern Interior of the province to the Lower Mainland and Vancouver Island, delivering clean, reliable power to customers.
- Construct a transmission line approximately 248-kilometers long, traversing some of BC’s rugged Coastal Range mountains and rising to an elevation of nearly 1,830 meters.
- Modify two existing terminal substations and construct a new series-capacitor substation to help maintain voltage levels across the long transmission line.
Solutions
- Working in an integrated team with BC Hydro and other external consultants, carried out construction program management services.
- Acted as BC Hydro's representative to manage the design-build contracts for implementation of the project.
- Ensured quality objectives were met by performing audits on each contractor, verifying conformance to contracts and in accordance with BC Hydro's quality management systems.
- Helped BC Hydro oversee project execution, to ensure problems were being discovered early, corrected adequately, and prevented from happening again.
Highlights
- The project included 248 km of 500 kV transmission line using 4-bundle conductor.
- We helped BC Hydro roll-out its new suite of project-controls applications for monitoring, control, and reporting on project progress.
- This was the first major BC Hydro transmission project to be administered using this new state-of-the-art project controls system.
Project numbers
248-kmtransmission line643lattice steel towers erected
2,960kilometers of conductor line
10,000tonnes of steel