170MWAC
920 acresin the harsh Southern Arizona desert
Over300 invertersystems
190,000metric tons of greenhouse gas emissions offset annually
Challenges
- The plant was experiencing unexpected operational issues after construction was complete.
- These operational issues had a significant impact on the site's energy production.
- A cross-functional team that consisted of Hatch, the constructor, and other consultants was formed to identify potential root causes.
Solutions
- We provided a small team of experienced engineers with unique and specialized skills specific to electrical grounding and large solar inverters.
- A detailed GAP analysis was developed and concerns were identified that related to system design specifications, grounding grid impedance measurements, fall potential readings, and system modeling.
Highlights
- One of the first utility solar power plants installed in the United States, it is larger than 100MW with future growth plans to reach 700MW.
- A complete review of the electrical grounding system design was carried out, which included nearly 500 documents and drawings.
- 独特的探讨isms and potential root causes were identified for the problems noted based on specific-to-large solar inverter know-how.
Project numbers
800,000 multicrystalline modules85,000 steel piers
300 US construction jobs
56,000 households powered
Expandable up to 700MW capacity
CAD$399M CAPEX
20-year power purchase agreement
Services & technologies provided
What's your challenge?
Related projects
Grand Falls Dam and Spillway Rehabilitation
Grand Falls, Newfoundland, Canada
bob华体会
British Columbia, Canada
Kelso Dam: urgent repairs and rehabilitation project
Milton, Ontario, Canada
Oxec II Hydroelectric Project
Guatemala
Rainy River Solar
Canada
Thunder Bay solar projects
Canada
Niagara Tunnel
Canada