NYPA Day Ahead Scheduling for St. Lawrence Power Project

Advanced optimization software schedules power generation by the hour

New York Power Authority | United States | 2015–2016

16个水电
generating units with optimized short-term generation schedules

Fewer
transitions while maintaining optimal dispatch

Stringent
water regulation requirements satisfied

Challenges

  • The New York Power Authority needed to replace the legacy short-term scheduling software used at its St. Lawrence project.
  • 软件had to work within the constraints of shared water-resource regulations between Canada and USA.
  • 水releases had to be perfectly balanced between the Canadian and American plants on a daily and weekly basis.

Solutions

  • STVista, the short-term scheduling module of Hatch'sVistaDSS™ decision-support software, will optimize short-term generation at NYPA's St. Lawrence power project.
  • New functionality was developed in the form of additional operating constraints and run-control options.
  • The software manages water rentals between both plants; implements multiple schedules for flat, daily peaking or weekly ponding operation; and transitions between non-navigation and navigation seasons.
  • A custom user interface was also developed to simplify the use of the model for day-to-day operation within the control room environment.

Highlights

  • Reduced the number of transitions, such as unit starts and stops, while maintaining optimal dispatch.
  • Significantly strengthened automated data exchange between the scheduling software and other NYPA systems.
  • Improved overall effectiveness of the scheduling process.

Project numbers

912 MWRobert Moses St. Lawrence Power Project in New York
16hydro generating units
1,045 MWat adjacent R.H. Saunders Generating Station in Ontario