Western Corridor Capacity Expansion
New, expanded tracks speed transport and boost trade
Canadian Pacific Railway (CP) | Canada
Conceptual, preliminary, and detailed design
160米llionconstruction cost
Challenges
- In response to a surge in trade with Asia, CP embarked on a $160 million track-expansion program between Moose Jaw, Saskatchewan and the Port of Vancouver, British Columbia.
- 26 separate double-track and siding-extension projects stretched across three Canadian provinces.
- Design sensitivity was exercised with respect to important First Nation and environmental issues.
Solutions
- Approximately 56 miles of new track were constructed, including 89 turnouts.
- Test plans, drawings, and software were created for 170 signal locations: shop-wired, 98; field- rewired, 72.
- A variety of civil design and construction techniques were used to address different issues in Prairie and Rocky Mountain terrain.
- 孵化’s services included conceptual, preliminary, and detailed design in the civil, track, signals, and communication disciplines, as well as program and construction management.
- Our services extended to developing tender packages, preparing bid evaluations, administering construction contracts and project controls.
Highlights
- The expansion increased capacity by 12 percent in Western Canada, representing an increase of about 400 freight cars per day.
- CPR selected Hatch on a sole-source basis to provide program, design, and construction management services to deliver this fast-track project.
- Several Hatch staff were awarded the CP Gold Ingenuity Award to commend them for their performance on the project.
Project numbers
- 160米llion construction cost.
- The expansion increased capacity by 12 percent in Western Canada, representing an increase of about 400 freight cars per day.
- 26 separate double-track and siding-extension projects stretched across three Canadian provinces.
- Approximately 56 miles of new track was constructed, including 89 turnouts.
What's your challenge?
Related projects

Technical Advisor for Electric Bus and Infrastructure Loans
York, Ontario, Canada

MaineDOT Bus Electrification Project
Maine, USA

Centerm Expansion Project
Vancouver, British Columbia, Canada

Caltrain Modernization Project
San Carlos, CA, USA