
USS Gary Works No. 8 Blast Furnace Reline
U.S. Steel | United States | 2010 - 2013
Completed
ahead of schedule
12%
final cost under-run of budget estimate
Challenges
- The project included the design and replacement of significant structural members, including the skip bridge and cold-blast main bridge.
- The hearth walls, which had not been replaced since 1995, the stack refractory, some cooling members, and a stove shell were also replaced.
- Various control systems had to be replaced, including the distributed control system, stove common programmable logic controller (PLC), and charging PLC.
- A significant change in scope in mid-FEL4 had to be accommodated. The change was incorporated without issue.
Solutions
- We provided engineering, procurement, and construction management services, including purchasing services, construction and safety management, and warehousing and materials management.
- 3D-engineering modeling was used, included laser scanning of the existing plant areas.
Highlights
- Engineering was completed on time.
- The project team had to adjust to a significant change in the scope in mid-FEL4, which was incorporated without issue.
- 反对struction was completed 2-½ days earlier than the planned 48-day outage, saving significant cost by avoided lost production.
“Well done from all areas of execution! Thanks for the continuous updates on the status throughout the outage.”
Project numbers
12%under-run of estimated cost2+天计划能满足故障的早期完成
What's your challenge?
Related projects

Tata Steel hydrogen-based steel manufacturing
IJmuiden, Netherlands
hth官方网址
Asia

SunCoke South Shore Project
United States

Anling 1700 mm Coilbox™
China

Clairton Improvement Project
United States
hth官网
South Africa

US Steel Mon Valley Works FFF System
United States